The inspector was out today and gave the okay to the power panel installation in the basement. The excavation team immediately arrived and began digging and trenching to support connection from the street service boxes to the house.
By the end of the afternoon, there are 2 trenches to the house; one to the power/cable/phone box, and the other to the gas line. The both meet at the side of the house to connect up to their own service port into the house.
The excavation gear was moved to the back of the house and dug the trench from the house to the well. The water lines are laid and enter into the house at the rear. When power is activated all the basement equipment for HVAC and water will be installed.
Wednesday, April 29, 2009
Tuesday, April 28, 2009
Siding, HVAC and Electric
The rear of the house and screened porch are now complete. The work now moves around the corner to the side with the dining and living rooms. The peak of the porch roof is a complementary, staggered, cedar shake that we will have in all the peaks and part of the front to add a nice, same color, contrasting texture.
The HVAC man is in the basement now installing the full length duct work to support all the smaller ducts extending along the ceiling to each room entrance point. Amazingly, he does everything on one foot.
The loft will have a ceiling fan and light at the cathedral peak to offer light and air flow to the loft and the living room below. By day’s end there are a myriad of wires running through all the walls and ceilings to support the switches, outlets, and recessed lighting.
The HVAC man is in the basement now installing the full length duct work to support all the smaller ducts extending along the ceiling to each room entrance point. Amazingly, he does everything on one foot.
The loft will have a ceiling fan and light at the cathedral peak to offer light and air flow to the loft and the living room below. By day’s end there are a myriad of wires running through all the walls and ceilings to support the switches, outlets, and recessed lighting.
Wednesday, April 22, 2009
Stairs and Siding
We have still been impacted by rainy days that have made for slight delays. However, the main stairway was delivered and by day’s end the entire framing team was available to raise them to the second floor.
The electrical work also began by laying out the locations of the wall outlets and switch boxes, and now that we can actually be in the space, we went around and nudged them slightly to better fit our needs. (no pix)
The siding team began and the detail needed to frame the windows and prepare for each piece of siding was more than imagined. The rear is attacked first and halfway done by late afternoon when the rains and thunder came back dramatically.
The electrical work also began by laying out the locations of the wall outlets and switch boxes, and now that we can actually be in the space, we went around and nudged them slightly to better fit our needs. (no pix)
The siding team began and the detail needed to frame the windows and prepare for each piece of siding was more than imagined. The rear is attacked first and halfway done by late afternoon when the rains and thunder came back dramatically.
Wednesday, April 15, 2009
Fireplace and Skylights
Roof Shingles and HVAC
Another rainy day, but the roofers were on site and began installing the shingles at the back of the house. By late morning they were done in the back, and had finished part of the front. Continuing rain prevented further completion.
The HVAC team arrived today as well. After some review of the framing location options, they gave use the lowdown on their approach. They made the cut-ins on the floor and along the walls, and installed insulation for those ducts on the exterior.
The plumbers were back finishing in the basement, and installing the smaller pipes in the bathrooms and kitchen. The French door from the dining room out onto the screened porch was installed, with the 3 living room skylights going in next.
The HVAC team arrived today as well. After some review of the framing location options, they gave use the lowdown on their approach. They made the cut-ins on the floor and along the walls, and installed insulation for those ducts on the exterior.
The plumbers were back finishing in the basement, and installing the smaller pipes in the bathrooms and kitchen. The French door from the dining room out onto the screened porch was installed, with the 3 living room skylights going in next.
Monday, April 13, 2009
Windows, Doors, and Plumbing
Today all the windows and exterior doors arrived. After a brief warm-up to put on the roof boards of the screened porch, they started installing windows at the rear of the house. It was a 2-man job to secure, level and nail in each window.
When the windows were done, then they began on the exterior doors. The lateness of the day only allowed the front door and the garage entrance door to the home office area just off the kitchen. The exterior garage door and basement entrance door are next.
While all this activity was going on, the plumbing team was in to rough-in the all the pipes for both bathrooms, the kitchen, the laundry area, and the pipe to the refrigerator. Tomorrow, down in the basement to finish things up.
When the windows were done, then they began on the exterior doors. The lateness of the day only allowed the front door and the garage entrance door to the home office area just off the kitchen. The exterior garage door and basement entrance door are next.
While all this activity was going on, the plumbing team was in to rough-in the all the pipes for both bathrooms, the kitchen, the laundry area, and the pipe to the refrigerator. Tomorrow, down in the basement to finish things up.
Sunday, April 12, 2009
Tar paper & Porches
With the roof boards all on, they started applying the tar paper in preparation for the roof shingles next week. The large exposed layer in the front roof is left until the 3 skylights are inserted next week when the windows and doors arrive.
The front porch was next with a lot of detail work needed to integrate the porch roof into the main roof. The porch is a basic front porch with pillars at the corners and a serpentine sidewalk to the driveway.
The rear screened porch was next. We will carry through the vaulted ceilings into the porch area for an airy, open feel with a great view. There will be several steps down to the small patio where a barbeque will be located.
The front porch was next with a lot of detail work needed to integrate the porch roof into the main roof. The porch is a basic front porch with pillars at the corners and a serpentine sidewalk to the driveway.
The rear screened porch was next. We will carry through the vaulted ceilings into the porch area for an airy, open feel with a great view. There will be several steps down to the small patio where a barbeque will be located.
Thursday, April 9, 2009
On goes the roof
More rain delayed the start of the roof, but today full speed ahead. The roof trusses were first, each supported properly with angle cross-braces. The various-length wall framing pieces were then cut to their own unique length to perfectly fit between the level wall top and the truss.
Then, more sheathing up to the peaks to finish the side walls and give further strength to the structure. Then the cornice was added to overhang the roof and allow water to drip off away from the house.
Then, more sheathing up to the peaks to finish the side walls and give further strength to the structure. Then the cornice was added to overhang the roof and allow water to drip off away from the house.
Friday, April 3, 2009
Second floor, please.
The rain was gone and the team started the exterior framing on the second floor. First the sill plate all around and then building and raising each portion into place. After a short while the rear walls were up and secure.
By early afternoon the side and front walls were also up; same process as before. Here’s a rear view showing Evan’s bedroom on the left and the loft on the right. Below is the office, kitchen and dining room.
By early afternoon the side and front walls were also up; same process as before. Here’s a rear view showing Evan’s bedroom on the left and the loft on the right. Below is the office, kitchen and dining room.
Wednesday, April 1, 2009
Second floor sub-floor
Today was tricky because it looked like it could rain any moment, dark and ominous – but the guys were there ready to go. The order of the day was to lay in the second floor sub-flooring and glue & nail it down. They first started over the dining room.
By late morning, and still no rain, so they were able to complete the full second floor. This went quite a bit faster since there will be no floor over the living room. There will be a cathedral ceiling similar to our previous home, which extends up over the dining room and above the second floor loft.
By noon things were getting darker and darker, so the guys prepped for tomorrow by lifting all the building materials onto the second floor. When that was done, the rains came.
By late morning, and still no rain, so they were able to complete the full second floor. This went quite a bit faster since there will be no floor over the living room. There will be a cathedral ceiling similar to our previous home, which extends up over the dining room and above the second floor loft.
By noon things were getting darker and darker, so the guys prepped for tomorrow by lifting all the building materials onto the second floor. When that was done, the rains came.
Subscribe to:
Posts (Atom)