Another rainy day, but the roofers were on site and began installing the shingles at the back of the house. By late morning they were done in the back, and had finished part of the front. Continuing rain prevented further completion.

The HVAC team arrived today as well. After some review of the framing location options, they gave use the lowdown on their approach. They made the cut-ins on the floor and along the walls, and installed insulation for those ducts on the exterior.

The plumbers were back finishing in the basement, and installing the smaller pipes in the bathrooms and kitchen. The French door from the dining room out onto the screened porch was installed, with the 3 living room skylights going in next.